5 November 2026 Empennage › Vertical stabilizer 3.5 h

Last session ended because I did not have a 1/8" drill bit available. Posted a question on Vans Airforce, and got a tip to use a 3.1 mm drill bit instead. Closest I could find was a 3.2mm, but this is still smaller than the final size so I figured it would be OK. 

Step 2: Used a 3.2mm drill instead of the 1/8" listed.

Step 4: Clecoing the hinges and hinge bracket was not so easy, the hole is too tight for a 4/32 cleco and too large for a 3/32 cleco. I ended up drilling up the holes of the brackets first, to a 4/32 so that they would stay in place.

Step 5: another place where imperial units in Norway is a challenge. The instruction says to use a #8 screw to temporarily hold things in place, normally norwegians does not have these things laying around. Found a screw in one of the subkits that fit OK though. 

Step 6: Now I am stuck due missing tools again, this time it's a 3/16"  drill bit (4.76mm). The final hole will be #12 (5.49mm). I can probablyt use a 5mm drill bit, but I will check another local hardware store first to see if they have "freedom unit" drill bits.  Imperial units really adds to the complexity and learning curve, because I have no internalized reference for these sizes. Hopefully I will get used to them at some point.

Bottom rudder hinge bracket clecoed in place. Had to drill up the holes a little to make the clecos fit. They were going to be upsized later anyways. 
During the inventory, I was missing only one piece, "E DRILL BUSHING". Even sent an email to vans to ask about it. Now I found it lodged inside the hinge bracket. So the delivery is complete!

 