| Section | Plans ref. | Status | Entries | Hours |
|---|---|---|---|---|
| Receipt and inventory | Complete | 2 | 7.5 | |
| Vertical stabilizer | Section 6 | Complete ✔ Approved | 6 | 21.5 |
| Rudder | Section 7 | Complete ✔ Approved | 7 | 23 |
| Horizontal stabilizer | Section 8 | Complete ✔ Approved | 7 | 27.5 |
| Elevators | Section 9 | Complete ✔ Approved | 7 | 25.5 |
| Tailcone | Section 10 | Complete ✔ Approved | 8 | 33.5 |
| Empennage attach | Section 11 | Complete ✔ Approved | 3 | 10 |
| Empennage fairings | Section 12 | Complete ✔ Approved | 3 | 7.5 |
Latest in Empennage
All entries →Empennage complete
Fairings done. The empennage is complete; on to the wings!
Rudder bottom fairing
Fitted the rudder bottom fairing and drilled for the tail light.
Empennage fairing
Trimmed the fiberglass fairing to fit around the HS and VS. Lots of sanding.
Elevators hung
Hung the elevators, set the control stops and safety-wired the bolts. All the empennage parts together for the first time.
VS and rudder fitted
Fitted the VS and hung the rudder. Rudder swings freely.